2023 – EPC OF FAST TRACK POWER PLANT PROJECT
Owner: Daewoo E&C
Implementing Company: AlMutajaded For Electric And Mechanical Works
Project: EPC OF FAST TRACK POWER PLANT PROJECT
Location: Karzar, Misrata.
Below are some pictures that demonstrate stages of disassembling and removal of old units and equipment for 4 units of type WH191.
ALMUTAJADED Signs with GECOL to implement several projects
ALMUTAJADED company is registered with the General Electricity Company (GECOL) and It was signed with her to implement several projects.
2023 – Proposal of the Establishment of JV Company
- Project Started on Jun 2023
- Project still under negotiation since 08 Jun 2023
2022 – Supply and installation of precast concrete building for GECOL
- Subcontractor: POMARAF, TUN Co.
Location: Tripoli
Prefabricated Electrical House | Integrated Power Distribution
2021 – Supply 2×7500 m3/day new desalination plant at KHPP2021
- Project location: AlKhums
- AL MUT Quoted for this Project on April 2022
- Wait for GECOL PO to Start the Project.
- See PIC
KH Supply and Install 2 MED Multiple Effect Distill Technology Desal Units
STEAM BOILER TWO PACKAGES
Installation of Two (2) Steam boiler PKM-64-80 and Auxiliaries
2021 – Rehabilitation of KHDP Unit 21
- Project location: Al-Khums
- AL MUT Quoted for this Project on 2021
- Owner (GECOL) Approval and PO Issued on 2022/09/21 GOV Resolution no# 828
- Wait for LC to Start the Project.
- See PIC
KH Desalination Plant Site Overview
Khoms Power Station
KH Desalination Plant Main Equipments
Agreement contract between Almutajaded and DAEWOO
An agreement contract was signed between Al Motajaded Company for the implementation of electrical and mechanical works and the Korean DAEWOO for Engineering Construction Company.